Which are objectives of the 'managing a stage boundary' process?

Which are objectives of the 'managing a stage boundary' process?

1. To control the link between the people managing the project and the people producing the products

2. To approve requests for change received during the completed stage

3. To provide information to the project board on the performance of the current stage

4. To review and, if necessary, update the project management team structure and role descriptions

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

PRINCE2 Prince2-Foundation Summary

  • Vendor: PRINCE2
  • Product: Prince2-Foundation
  • Update on: Jul 25, 2025
  • Questions: 461
Price: $52.5  $149.99
Buy Now Prince2-Foundation PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method