Which statement about the 'manage by stages’ principle is CORRECT?

Which statement about the 'manage by stages’ principle is CORRECT?

A.

The project board should authorize multiple stages at the same time

B.

The end of a stage should provide a control point for the project board

C.

A project should have fewer, longer stages when the risk exposure is high

D.

A project should have separate stages to plan, deliver and close the project