Why does the project board review the PID during an end stage assessment?

Why does the project board review the PID during an end stage assessment?

A.

To confirm that project controls are adequate for the remainder of the project

B.

To notify the commissioning organization that the project has been authorized

C.

To review summarized progress to date and decide what to do next with the project

D.

To ensure that post-project reviews of operational performance are planned

PRINCE2 Prince2-Foundation Summary

  • Vendor: PRINCE2
  • Product: Prince2-Foundation
  • Update on: Jul 25, 2025
  • Questions: 461
Price: $52.5  $149.99
Buy Now Prince2-Foundation PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method