It is now late October and the project is in stage 3.

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.

There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

Which product should show that the project has been closed prematurely and has not achieved the objectives defined in the Project Initiation Documentation (PID)?

A.

Benefits Review Plan

B.

End Project Report

C.

Exception Report

D.

Project closure notification

PRINCE2 Prince2-Practitioner Summary

  • Vendor: PRINCE2
  • Product: Prince2-Practitioner
  • Update on: Jul 25, 2025
  • Questions: 282
Price: $52.5  $149.99
Buy Now Prince2-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method