The chair of a quality review meeting advised the Team Manager that, because there were...

The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance.

Which 2 actions should the Team Manager take in response to this situation?

A.

Ask the reviewers to work overtime to prevent the delay.

B.

Ensure that the situation is included in the next Highlight Report.

C.

Raise an issue explaining that tolerances are forecast to be exceeded.

D.

Advise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.

E.

Ensure that the Quality Register is updated with the quality review result.

PRINCE2 Prince2-Practitioner Summary

  • Vendor: PRINCE2
  • Product: Prince2-Practitioner
  • Update on: Jul 25, 2025
  • Questions: 282
Price: $52.5  $149.99
Buy Now Prince2-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method