PRINCE2 Prince2-Practitioner Question Answer
The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance.
Which 2 actions should the Team Manager take in response to this situation?
PRINCE2 Prince2-Practitioner Summary
- Vendor: PRINCE2
- Product: Prince2-Practitioner
- Update on: Jul 25, 2025
- Questions: 282