Two weeks after starting work the Team Manager noticed that each completed product had exceeded...

Two weeks after starting work the Team Manager noticed that each completed product had exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed its agreed cost tolerance of 5%.

Which 2 actions should the Team Manager take in response to this situation?

A.

Check the status of the products currently being worked on and analyze the effort expended, to determine if the trend is continuing.

B.

Update the Team Plan by increasing all future work estimates by 10%.

C.

Amend the Work Package and ensure that the revised targets are met.

D.

Escalate the situation in the next Checkpoint Report.

E.

Raise an issue that costs will exceed tolerance if the current trend continues.

PRINCE2 Prince2-Practitioner Summary

  • Vendor: PRINCE2
  • Product: Prince2-Practitioner
  • Update on: Feb 7, 2026
  • Questions: 263
Price: $52.5  $149.99
Buy Now Prince2-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method