During the sprint the developers realize that they have selected too many product backlog items.

During the sprint the developers realize that they have selected too many product backlog items. How should they go from there?

A.

Inform the product owner and the stakeholders during the sprint review

B.

As soon as they realize they should work with the product owner to remove some work while not endangering the sprint goal

C.

Outsource the work to another team

D.

Use a definition of done with lower standards to be able to finish all the work they committed to

Scrum PSD Summary

  • Vendor: Scrum
  • Product: PSD
  • Update on: Jul 30, 2025
  • Questions: 163
Price: $52.5  $149.99
Buy Now PSD PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method