For the purpose of transparency, when does Scrum say a new increment of working software...

For the purpose of transparency, when does Scrum say a new increment of working software must be available?

A.

After the acceptance testing phase.

B.

Before the release Sprint.

C.

Every 3 Sprints.

D.

At the end of every Sprint.

E.

When the Product Owner asks to create one.