The CEO asks the Developers to add a " very important " item to a...

The CEO asks the Developers to add a " very important " item to a Sprint that is in progress.

What should the Developers do?

(choose the best answer)

A.

Add the item to the top of the Product Backlog.

B.

Add the item to the current Sprint Backlog and begin work immediately since the

request came from the CEO.

C.

Add the item to the Sprint Backlog for the next Sprint.

D.

Discuss the item with the other members of the Scrum Team so the team can

decide what to do.

E.

Add the item to the current Sprint and drop an item of equal size.

Scrum PSM-I Summary

  • Vendor: Scrum
  • Product: PSM-I
  • Update on: Mar 24, 2026
  • Questions: 296
Price: $52.5  $149.99
Buy Now PSM-I PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method