When do Development Team members take ownership of a Sprint Backlog item?

When do Development Team members take ownership of a Sprint Backlog item?

A.

At the Sprint planning meeting.

B.

During the Daily Scrum.

C.

Never. All Sprint Backlog Items are “owned” by the entire Development Team, even though each one may be done by an individual Development Team member.

D.

Whenever a team member can accommodate more work.