When must a Product Owner release each Increment?

When must a Product Owner release each Increment? (Choose the best answer.)

A.

When it makes sense.

B.

When the Scrum Team finishes their work.

C.

Whenever the product is free of defects.

D.

After every Sprint, Without exception.