Which two things should the Development Team do during the first Sprint?

Which two things should the Development Team do during the first Sprint? (Choose two.)

A.

Make up a plan for the rest of the project.

B.

Analyze, describe, and document the requirements for the subsequent Sprints.

C.

Develop at least one piece of functionality.

D.

Define the major product features and release plan architecture

E.

Create an increment of potentially releasable software.