At the seventh Sprint Review, the stakeholders seem disappointed and angry.

At the seventh Sprint Review, the stakeholders seem disappointed and angry. When asked about it, they say the product being built will not meet their needs and will cost more than they anticipated spending. What factors may have led to this?

(choose the best three answers)

A.

The stakeholders have not been using the Sprint Reviews to actively engage, and inspect and evaluate progress.

B.

The stakeholders were not allowed to enter the development area, or be present at the Daily Scrum.

C.

The Project Management Office (PMO) and its project managers have not been adequately engaged, causing the project plan to become inaccurate.

D.

The Scrum Master has not ensured transparency.

E.

The Product Owner has not been interacting frequently with the stakeholders and kept them aware of the progress of the project.

F.

Changes to the project plan were not adequately documented and shared. The change request procedure was not diligently followed.

Scrum PSM-II Summary

  • Vendor: Scrum
  • Product: PSM-II
  • Update on: Jul 28, 2025
  • Questions: 74
Price: $52.5  $149.99
Buy Now PSM-II PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method