Towards the end of Sprint Planning, the Product Owner and the Developers have not been able to reach a clear, mutual understanding about the highest order Product Backlog items. Because of this, the Developers could not figure out how many Product Backlog items they could forecast for the upcoming Sprint. The Product Owner did make it clear what business objective he is hoping to achieve with this Sprint. Which of the following two actions would you support?