Activity 2003 started during the current reporting period and proceeded as planned with the normal...

Activity 2003 started during the current reporting period and proceeded as planned with the normal schedule. If the remaining duration at the end of this period is ten workdays, then what is the earned value assignable to Activity 2003 in the pay estimate for this reporting period?

A.

$6,000

B.

$10.000

C.

$5,000

D.

$8,000