Assuming that you had only one crane capable of 30 lifts per day, 3 column...

Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

A.

8 work days

B.

18 work days

C.

7 work days

D.

15 workdays