Due to a testing delay, release of the product for manufacture is delayed by 5...

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

A.

15 days.

B.

0 days.

C.

5 days.

D.

10 days.