If a detailed estimate is NOT available to assist in the formulation of activity durations...

If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

A.

The Eichleay formula

B.

Historical production rates

C.

Time impact analysis

D.

Black-Scholes model