If Activity A was delayed 5 days from starting, which of the following adjustments will...

If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?

A.

Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from B' to 'C with FSO.

B.

Replace the relationship from 'B’ to 'C’ with SSO

C.

Reduce the duration of B" from 10 days to 5 days by compressing work effort

AACE International PSP Summary

  • Vendor: AACE International
  • Product: PSP
  • Update on: Oct 31, 2025
  • Questions: 216
Price: $52.5  $149.99
Buy Now PSP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method