Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

A.

Estimating remaining durations of activities.

B.

The correct recording of actual start dates.

C.

Making "downstream" logic revisions as required.

D.

Entering the time impacts of delays and change orders.