AACE International PSP Question Answer
Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?
AACE International PSP Summary
- Vendor: AACE International
- Product: PSP
- Update on: Oct 31, 2025
- Questions: 216


 
 