When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT...

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

AACE International PSP Summary

  • Vendor: AACE International
  • Product: PSP
  • Update on: Jul 27, 2025
  • Questions: 163
Price: $52.5  $149.99
Buy Now PSP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method