During a Sprint, when is new work or further decomposition of work added to the...

During a Sprint, when is new work or further decomposition of work added to the Sprint

Backlog?

(choose the best answer)

A.

During the Daily Scrum after the Developers approve it.

B.

When the Scrum Master has time to enter it.

C.

When the Product Owner identifies new work.

D.

As soon as possible after it is identified.