Summer Special Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: vce65

During a Sprint, when is new work or further decomposition of work added to the...

During a Sprint, when is new work or further decomposition of work added to the Sprint

Backlog?

(choose the best answer)

A.

During the Daily Scrum after the Developers approve it.

B.

When the Scrum Master has time to enter it.

C.

When the Product Owner identifies new work.

D.

As soon as possible after it is identified.

Scrum PSPO-I Summary

  • Vendor: Scrum
  • Product: PSPO-I
  • Update on: Jul 20, 2025
  • Questions: 177
Price: $52.5  $149.99
Buy Now PSPO-I PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method