How much time is required after a Sprint to prepare for the next Sprint?

How much time is required after a Sprint to prepare for the next Sprint?

(choose the best answer)

A.

The break between Sprints is timeboxed to one-week for a one-month Sprint, and

usually less for shorter Sprints.

B.

Enough time for the requirements for the next Sprint to be determined and

documented.

C.

Enough time for the Developers to finish the testing from the last Sprint.

D.

None. A new Sprint starts immediately following the end of the previous Sprint.

E.

All of the above are allowed depending on the situation.

Scrum PSPO-I Summary

  • Vendor: Scrum
  • Product: PSPO-I
  • Update on: Jul 20, 2025
  • Questions: 177
Price: $52.5  $149.99
Buy Now PSPO-I PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method