When should the Product Owner update the project plan?

When should the Product Owner update the project plan?

(choose the best answer)

A.

After the Daily Scrum to ensure an accurate daily overview of project progress.

B.

The project plan must be updated prior to the Sprint Retrospective.

C.

The Product Backlog is the plan in Scrum. It is updated as new information and

insights emerge.

D.

Before the Sprint Planning to know how much work will have to be done in the Sprint.

Scrum PSPO-II Summary

  • Vendor: Scrum
  • Product: PSPO-II
  • Update on: Jul 20, 2025
  • Questions: 83
Price: $52.5  $149.99
Buy Now PSPO-II PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method