Who is accountable for clearly expressing Product Backlog items?

Who is accountable for clearly expressing Product Backlog items?

(choose the best answer)

A.

The Developers.

B.

The Scrum Master.

C.

The Scrum Master, or the Scrum Master may have the Developers help.

D.

The Product Owner, but the Product Owner may appoint a proxy on the Scrum Team to do the work.

E.

The Scrum Master, or the Scrum Master may have the Product Owner do it.