What is the PERT estimate of time for cable placement on a given job?

What is the PERT estimate of time for cable placement on a given job?

- Optimistic time is 100 hours

- Most likely time is 125 hours

- Pessimistic time is 210 hours

A.

100 hours

B.

125 hours

C.

135 hours

D.

155 hours

E.

175 hours