A global communications company's cloud-based platform will host its video network using both on - and off-shore learns. The program management office (PMO) assigns a program manager with little experience executing global initiatives.

What should the program manager do to resolve competing resource needs within components that could impact the entire program's overall delivery date?

A.

Require project managers to perform resource levelling in their schedules to automatically take into account availability and dependencies tor key resources.

B.

Revisit assignments on a weekly basis to manually level resources thereby limiting burn-out and preventing underutilization

C.

Optimize integration of the component projects by working with the project managers to align resource skill sets and availability to the program

D.

Improve communications between the project managers to gain efficiencies in resource assignments

BICSI RCDDv14.1 Summary

  • Vendor: BICSI
  • Product: RCDDv14.1
  • Update on: Aug 1, 2025
  • Questions: 320
Price: $52.5  $149.99
Buy Now RCDDv14.1 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method