A Scrum Team is estimating the prioritized User Stories. Each team member has been assigned a deck of
numbered cards, in which each card is numbered in a sequence. The team members use these cards to
assess a particular User Story by picking and showing a card from the deck that represents their estimate for
the User Story. Which estimation tool is the Scrum Team using?