Refer to the exhibit.
Data for October's budget for product Quest for the month of October are given below:
Each unit of Quest requires 6kg of raw materials. Strict quality control procedures are applied to the manufacturing process and normal rejection levels are 5% of finished units.
The raw materials purchases budget for the month of October is: