Refer to the exhibit.

Refer to the exhibit.

The budget for ORG for the month of September contained the following data:

During the month the actual number of units produced was 1,550. The management accounts showed a direct labour rate variance of $200 adverse and direct labour efficiency variance of $150 adverse.

The actual direct labour hours in the month was:

A.

1,312.5 hours

B.

1,125 hours

C.

1,200 hours

D.

1,012.5 hours

CIMA BA2 Summary

  • Vendor: CIMA
  • Product: BA2
  • Update on: Jul 29, 2025
  • Questions: 392
Price: $52.5  $149.99