A project has an EV of 100 workdays, an AC of 120 workdays, and a...

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?

A.

There is a cost underrun.

B.

There is a cost overrun.

C.

The project may not meet the deadline.

D.

The project is 20 days behind schedule.