Which of the following statements is correct?

Which of the following statements is correct?

A.

Contract documents are complementary

B.

Requirement of one of the contract documents may be superseded by others

C.

Specifications take precedence over drawings

D.

The architect/engineer may require the contractor to perform at a higher level than the contract documents require