New Year Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmasmnth

Which of the following statements is correct?

Which of the following statements is correct?

A.

Contract documents are complementary

B.

Requirement of one of the contract documents may be superseded by others

C.

Specifications take precedence over drawings

D.

The architect/engineer may require the contractor to perform at a higher level than the contract documents require

Construction Specifications Institute CDT Summary

  • Vendor: Construction Specifications Institute
  • Product: CDT
  • Update on: Jan 10, 2026
  • Questions: 120
Price: $52.5  $149.99
Buy Now CDT PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method