Which of the following is built by aggregating the costs of the individual work elements...

Which of the following is built by aggregating the costs of the individual work elements and then joining them at time intervals where meaningful actual cost information will be available?

A.

Cost baseline

B.

Cost estimation

C.

Cost controlling

D.

Cost budgeting