Don has hired Jerry, a contractor, to complete a portion of his project work.

Don has hired Jerry, a contractor, to complete a portion of his project work. The contract used was a cost-plus contract. If Don was to perform a risk audit, who would carry the risk in this scenario?

A.

Jerry would because he is the hired contractor.

B.

Don would because he is the project manager.

C.

Don would because of the contract type.

D.

Jerry would because of the contract type.