Mark works as a project manager for the SLQ Project.

Mark works as a project manager for the SLQ Project. He is working with the project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique will Mark use to achieve the above task?

A.

Predecessor and successor diagramming

B.

System or process flow chart

C.

Influence diagram

D.

Cause and effect diagram