You are project manager of HHK project.

You are project manager of HHK project. Examine the network diagram given below: A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?

A.

Five days

B.

Four days

C.

Six days

D.

Zero, it is on the critical path.