You are the project manager for your organization.

You are the project manager for your organization. Your organization manages projects for other companies. You will be soon managing a project for the JUH Company. What document do you need first to help to develop the project charter?

A.

Business requirements

B.

Functional requirements

C.

Preliminary project scope statement

D.

Contract