GIAC GCPM Question Answer
You work as a project manager for PassGuide Inc. You are working with your project team to plan the risk responses. Your project has a budget of $450,000 and is expected to last seven months. You have identified a risk event that has a probability of .60 and has a cost impact of $250,000 within the project. While creating a risk response for this event, what is the risk exposure of the event that must be considered for the cost of the risk response?