You work as a project manager for PassGuide Inc. You want to calculate the minimum completion time for a project along with the possible start and finish times for the project activities. Which of the following techniques will you use to accomplish the task?

A.

Time-oriented scheduling

B.

Network scheduling

C.

Critical path scheduling

D.

Resource-oriented scheduling