You work as a project manager for BlueWell Inc.

You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased from the outside sources?

A.

Contract Types

B.

Make-or-Buy Analysis

C.

Procurement Negotiations

D.

Expert Judgment