You work as a project manager for PassGuide Inc. You do not want to change the task relationship, but you require a "waiting time" before the starting of the activity can begin. Which of the following is the best approach to alleviate this issue?

A.

Add management reserve to the project activities.

B.

Add lag time to the project activities.

C.

Add lead time to the project activities.

D.

Add float to the project activities.