You work as the project manager for Bluewell Inc.

You work as the project manager for Bluewell Inc. You are working on NGQQ Project for your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?

A.

Risk acceptance

B.

Risk avoidance

C.

Risk transference

D.

Risk mitigation

GIAC GCPM Summary

  • Vendor: GIAC
  • Product: GCPM
  • Update on: Jul 25, 2025
  • Questions: 397
Price: $52.5  $149.99
Buy Now GCPM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method