ISM INTE Question Answer
A manufacturing firm prepares the following materials requirement plan (MRP):
Master Production Schedule
Week123456
Item A101015152020
Relevant Information
ItemItem's ParentItem's Lead TimeItem's Lot SizeItem's Current Inventory
ANone1 weekLFL50
BA2 weeks5010
CB2 weeks5010
Using MRP methodology, how much of Item B should be ordered, and when should it be ordered7