A manufacturing firm prepares the following materials requirement plan (MRP):Master Production ScheduleWeek123456Item A101015152020Relevant InformationItemItem's ParentItem's...

A manufacturing firm prepares the following materials requirement plan (MRP):

Master Production Schedule

Week123456

Item A101015152020

Relevant Information

ItemItem's ParentItem's Lead TimeItem's Lot SizeItem's Current Inventory

ANone1 weekLFL50

BA2 weeks5010

CB2 weeks5010

Using MRP methodology, how much of Item B should be ordered, and when should it be ordered7

A.

50 items immediately and 50 items in week 3

B.

20 items in week 4 and 20 items in week 5

C.

10 items in week 2 and 20 items in week 3

D.

50 items in week 2

ISM INTE Summary

  • Vendor: ISM
  • Product: INTE
  • Update on: Jul 21, 2025
  • Questions: 167
Price: $52.5  $149.99
Buy Now INTE PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method