How should risk be managed in the Intolerable region?

How should risk be managed in the Intolerable region?

A.

Risk cannot be justified except in extraordinary circumstances.

B.

Risk is tolerable only if risk reduction is impracticable or its cost is grossly disproportionate to the improvement gained.

C.

Risk is tolerable if the cost of reducing it would exceed the benefit.

D.

Risk can be accepted if monitored closely.

PECB ISO-31000-Lead-Risk-Manager Summary

  • Vendor: PECB
  • Product: ISO-31000-Lead-Risk-Manager
  • Update on: Jan 18, 2026
  • Questions: 80
Price: $52.5  $149.99
Buy Now ISO-31000-Lead-Risk-Manager PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method