New Year Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmasmnth

You are working as a project manager in your organization.

You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?

A.

Quantitative risk analysis

B.

Qualitative risk analysis

C.

Requested changes

D.

Risk audits

ISC ISSMP Summary

  • Vendor: ISC
  • Product: ISSMP
  • Update on: Dec 14, 2025
  • Questions: 218
Price: $52.5  $149.99
Buy Now ISSMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method