CIPS L4M1 Question Answer
Describe the main stages of the CIPS Procurement and Supply Cycle (25 points)
The Answer Is:
See the solution in Explanation part below.
This question includes an explanation.
Explanation:
How to respond to this question:
- Include as many of the stages as you can, but it’s not vital to remember them all. You should aim to remember at least 8 of the 13 steps.
- The steps are; Define Business Need, Market Analysis + Make vs Buy, Develop Strategy and Plan, Pre-Procurement Market Testing, Develop Documents and Specification, Supplier Selection, Issue Tender, Bid Evaluation, Contract Award and Implementation, Warehouse Logistics, Contract performance and Improvement, Supplier Relationship Management and Asset Management
Essay Plan:
Introduction - Explain what the CIPS Procurement and Supply Cycle is- a tool to be used by procurement professionals which tracks a procurement exercise from inception to close. It’s helpful as it ensures procurement exercises are done correctly and steps are completed in the right order.
- Describe (briefly) what happens at each stage of the cycle, giving examples. You should put each stage into a separate paragraph. It’s also a good idea to name the stages in chronological order. Some ideas of things you could mention include:
1) Define Business Need and Develop Specification - Identify what the need is, what type of purchase, put together a business case and outline the requirements
2) Market Analysis and Make vs Buy Decision – analyse the market using market segmentation (e.g. by buyer, product, geography etc) or use Porter’s 5 Forces (buyer and supplier power, threat of new entrants, threat of substitutions, supplier rivalry). Looks at if what you want to procure is actually available.
3) Develop Strategy / Plan – you could use a STEEPLE and SWOT analysis. Consider if this is the right time to procure. Create timelines and budgets.
4) Pre-Procurement Market Testing - consider stakeholder engagement, supplier engagement, new / upcoming legislation, currency fluctuations, market, competitor actions. Is this the best time to procure? Will it be successful?
5) Develop Documentation / Creation of Contract terms- firm up the requirements and create the formal documents for the tender exercise. This may be a RFQ or ITT. Define the offer. Include KPIs.
6) Supplier Selection – May not be required for rebuys but an important step for new buys. May use a list of pre-approved suppliers or this may be going out to the open market. You can shortlist suppliers by sending out a pre-qualification questionnaire.
7) Issue Tender - Electronically, consider whether to use an open vs closed procurement exercise
8) Bid / Tender Evaluation – Very flexible for companies in the private sector but there are guiding principles for doing this for public procurement; transparency, equal treatment, proportionality. Often considers both price and quality.
9) Contract Award and Implementation- Organisations may have different processes for different values (e.g. large purchases may need senior management approval, but under £500 just needs a manager’s signature). May require post-award negotiation. Contract is drafted and signed.
10) Warehouse Logistics and receipt – includes POs and Invoices. Battle of the Forms. Goods Inwards = receiving and inspecting goods- may use quality control.
11) Contract performance review - ensuring contract obligations are fulfilled includes P2P procedures, database management, budgeting / costs monitoring, reporting and dispute resolution.
12) Supplier Management – will depend on the relationship but includes; contact / meetings with the supplier, motivating / incentivising the supplier, working with them on performance issues, ensuring KPIs are met.
13) Asset Management / End of Life- considers TCO, ongoing maintenance and costs, insurance and warrantees and disposal of the item once it has reached the end of its life.
Conclusion – The CIPS Procurement Cycle is cycle rather than process as it is a continuous loop and needs constantly emerge. It never ends. New buys are more likely to follow all the stages of the cycle, rebuys may skip steps
Tutor Notes:
- Often steps 11 and 12 are confused or merged together but they are different. It’s possible to have great contract management and a poor supplier relationship i.e. the contract is working effectively and the supplier is delivering in line with the contract BUT the relationship may be fraught with tension and the buyer and supplier don’t like each other.
- To get a high score I would include examples of all of the stages, but remember you only have 45 minutes to answer the question, so balance detail with timing so you don’t overwrite
- The procurement cycle is on p. 70 or you can download it here: Procurement Supply Cycle | CIPS