The programme has successfully completed all projects and work according to the delivery plan and...

The programme has successfully completed all projects and work according to the delivery plan and is in the ‘close the programme' process. All internal staff, who had worked on the programme, must now be transferred back into business as usual roles.

Which role should be responsible for managing these activities?

A.

Sponsoring group members

B.

Senior responsible owner

C.

Programme manager

D.

Business change manager

PeopleCert MSP-Practitioner Summary

  • Vendor: PeopleCert
  • Product: MSP-Practitioner
  • Update on: Feb 21, 2026
  • Questions: 133
Price: $52.5  $149.99
Buy Now MSP-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method