The programme is in Tranche 2 and has been progressing according to plan.

The programme is in Tranche 2 and has been progressing according to plan. However, there have been difficulties transitioning to the new ways of working at the end of Tranche 1 and UU has had some customer complaints as a result. Therefore, the SRO asked the programme manager to replan the programme so that all remaining capabilities are transitioned at the end of the programme, instead of at the end of the tranche.

Is this an appropriate application of the 'structure' theme, and why?

A.

Yes, because applying the ‘lead with purpose’ principle requires delivery to be planned to realize outcomes of benefit

B.

Yes, because applying the 'collaborate across boundaries' principle requires effective use of programme resources

C.

No, because applying the ‘realize measurable benefits’ principle requires outcomes of benefit to be embedded at intermediate landing points

D.

No, because applying the ‘align with priorities' principle requires the content of the tranches to be changed, rather than delaying transition

PeopleCert MSP-Practitioner Summary

  • Vendor: PeopleCert
  • Product: MSP-Practitioner
  • Update on: Feb 21, 2026
  • Questions: 133
Price: $52.5  $149.99
Buy Now MSP-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method