A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered...

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

A.

Finish-to-start

B.

Start-to-start

C.

Finish-to-finish

D.

Start-to-finish